Timeline:
Custom &
Pre-Designed
Plans

Construction Timeline
Pre-Designed &
Custom Plans

Knowing where you are going and how long it will take to get there is an essential part of any journey. The first step we take is to set realistic expectations regarding design, financing, and construction so that we can move through the process efficiently and effectively together. Our team is here to help make sure the timeline stays on track and up to date.

Below we break down the timeline of construction for a custom plan that we design in collaboration with a client, versus one for an EcoCraft predesigned plan. Together, we can bring your dream home into reality!

Custom
Plans

Total Timeline
14-23 Months

Average
14 Months

PHASE 1
Pre-Construction Planning
6-16 Weeks

PHASE 2
Financing & Permitting
5-8 Months

PHASE 3
Construction
6-8 Months

PHASE ONE: PRE-CONSTRUCTION PLANNING (3-7 MONTHS)

Onboarding concept design, schematic design, and design development/pricing

PHASE TWO: FINANCING AND PERMITTING (5-8 MONTHS)

Timeline Depends on Bank and Local Municipality/State Building Requirements

PHASE THREE: CONSTRUCTION (6-8 MONTHS)

EcoCraft Full Service, timeline depends on size and complexity of the project

Pre-Designed
Plans

Total Timeline
10-20 Months

Average
10 Months

PHASE 1
Pre-Construction Planning
6-16 Weeks

PHASE 2
Financing & Permitting
5-8 Months

PHASE 3
Construction
4-8 Months

PHASE ONE: PRE-CONSTRUCTION PLANNING (6-16 WEEKS)

Design and selections, Onboarding

PHASE TWO: FINANCING AND PERMITTING (5-8 MONTHS)

Timeline Depends on Bank and Local Municipality/State Building Requirements

PHASE THREE: CONSTRUCTION (4-8 MONTHS)

EcoCraft Full Service, timeline depends on size and complexity of the project