Knowing where you are going and how long it will take to get there is an essential part of any journey. The first step we take is to set realistic expectations regarding design, financing, and construction so that we can move through the process efficiently and effectively together. Our team is here to help make sure the timeline stays on track and up to date.
Below we break down the timeline of construction for a custom plan that we design in collaboration with a client, versus one for an EcoCraft predesigned plan. Together, we can bring your dream home into reality!
Custom
Plans
Total Timeline
14-23 Months
PHASE 1
Pre-Construction Planning
6-16 Weeks
PHASE 2
Financing & Permitting
5-8 Months
PHASE 3
Construction
6-8 Months
PHASE ONE: PRE-CONSTRUCTION PLANNING (3-7 MONTHS)
Onboarding concept design, schematic design, and design development/pricing
Conceptual Design - 2 -4 weeks
Schematic Design- 6-14 weeks
Contracting 4-10 weeks
PHASE TWO: FINANCING AND PERMITTING (5-8 MONTHS)
Timeline Depends on Bank and Local Municipality/State Building Requirements
PHASE THREE: CONSTRUCTION (6-8 MONTHS)
EcoCraft Full Service, timeline depends on size and complexity of the project
Pre-Designed
Plans
Total Timeline
10-20 Months
PHASE 1
Pre-Construction Planning
6-16 Weeks
PHASE 2
Financing & Permitting
5-8 Months
PHASE 3
Construction
4-8 Months
PHASE ONE: PRE-CONSTRUCTION PLANNING (6-16 WEEKS)
Design and selections, Onboarding
PHASE TWO: FINANCING AND PERMITTING (5-8 MONTHS)
Timeline Depends on Bank and Local Municipality/State Building Requirements
PHASE THREE: CONSTRUCTION (4-8 MONTHS)
EcoCraft Full Service, timeline depends on size and complexity of the project